Summary
Nearly 95% of India’s trade by volume, and about 70% by value, moves by sea. The fuel in our vehicles, the coal in our power plants and the phones in our hands all arrive through ports that most people never see.
This paper explains India’s maritime system as infrastructure: the ports, ships, yards, routes and institutions, who builds and runs them, and how they pay for themselves. Its central finding is an imbalance. India has built strong gateways, but it owns, builds and repairs few of the ships that use them.
Six findings
- The gateways are the strongest part.Indian ports handled about 1,668 million tonnes of cargo in FY26, a third more than five years earlier. Mundra became the first Indian port to handle more than 200 million tonnes in a year.
- Capacity on paper is not capacity in use.Capacity has been added faster than cargo, so only about 58% of India’s rated port capacity was used in FY25. Among major ports, use ranged from 79% at Mumbai to 29% at Mormugao.
- The ships and yards are the weakest part.Indian ships carried 40.7% of the country’s trade in 1987-88 and about 7.8% by 2018-19. Indian yards build about 0.06% of the world’s new ships and repair less than 1%.
- India supplies the crews and breaks up the ships.Indian seafarers make up about 12% of the global workforce, and India recycled 35.4% of the world’s ships in 2025, more than any other country.
- The routes are changing fast.Cargo on National Waterways rose from about 84 million tonnes in FY21 to 218 million in FY26. Vizhinjam, India’s first deep-water transshipment port, handled 1.30 million TEU in its first full year.
- Much of the delay sits outside the port.Export cargo at seaports waited about 158 hours after customs clearance in 2025, against about 30 hours for the clearance itself.
The answer is a system with strong gateways and weak ownership.From the paper’s conclusion
The evidence
Three streams dominate what India’s ports move. In FY25 petroleum made up about 27% of all cargo, coal about 22% and containers about 22%. Most people picture containers, but petroleum and coal together carry about half the tonnage, and each needs a very different kind of port.
The estate has two tiers. Twelve major ports owned by the Centre handled about 55% of cargo in FY26; the states regulate 217 notified non-major ports, of which about 68 handle cargo. Gujarat alone handles about two in every five tonnes.
- Share of world shipbuilding, 2024
- 0.06%
- Share of world ship repair
- <1%
- Share of world ship recycling, 2025
- 35.4%
- Share of global seafarers
- ~12%
India’s fleet stood at 1,592 vessels at the end of 2025, and nearly half of all registered vessels are more than 20 years old. Sources: Ministry of Ports, Shipping and Waterways; Directorate General of Maritime Administration.
Port economics are front-loaded. Almost all the cost is spent before the first ship arrives, while revenue comes in over 30 years or more, so use rather than size decides returns. In FY26 Adani Ports and SEZ reported an operating margin of about 59% and JSW Infrastructure about 49%. Ships and yards face harder economics, which is why the state now supports them directly, starting with a Rs 69,725 crore package approved in September 2025.
Ports do not choose their cargo. For bulk cargo the buyer decides; for containers, the shipping lines do. A port that fails on cargo type, depth, connectivity or total cost can sit half empty even while the country’s trade grows.
| Project or programme | Scale | Status |
|---|---|---|
| Vadhavan, Maharashtra | 298 MTPA, including 23.2 million TEU; Rs 76,220 crore | Approved June 2024; first phase due by 2030 |
| Vizhinjam expansion, Kerala | Several times its first-phase capacity of about 1 million TEU | Targeted for 2028 |
| Mundra phase 3, Gujarat | 196 MTPA; Rs 25,000 crore | Project report under scrutiny |
| Shipbuilding and maritime package | Rs 69,725 crore; target of 4.5 million GT a year | Approved September 2025 |
| National Waterways | 20 new waterways to be made operational | Announced in Union Budget 2026-27 |
Plans and targets are not commitments. Vadhavan and the proposed third phase at Mundra are of similar size and aim at the same cargo, so not all of it will fill at once. Sources: Union Cabinet; Ministry of Ports, Shipping and Waterways; company disclosures.
The system is also exposed to shocks far from India’s coast. In 2026 conflict in the Gulf disrupted shipping through the Strait of Hormuz, and container congestion built up at west coast ports within weeks.
What leaders must weigh
- Maritime decisions outlast strategies.Vadhavan spans close to two decades from notification to build-out, and concessions run for 30 years. Will this decision still make sense when today’s strategy has changed?
- Capacity on paper is not capacity in use.What can this port actually handle for my cargo, at my volumes, today?
- Depth and connectivity decide relevance.Can this port or route take the ships my trade is moving to, and move cargo inland quickly?
- Dependence on foreign ships and hubs is a risk.What is my fallback if a route, port or foreign carrier fails?
- The energy transition will shift cargo.Petroleum and coal are about half of port cargo. How exposed are my port and route choices to a decline in fossil cargo?
The full paper covers how the system was built, each part of it in turn, who runs it and sets the rules, and the sources behind every figure. For how we work with energy and commodity companies on energy leadership, see our sector page.